Mangaldeep Associates & Developers
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vaishnave ClassicP52100019954 | Pimpri Chinchawad (M Corp.) | 2019 | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| Harsh ApartmentP52100025753 | Pimpri Chinchawad (M Corp.) | 2020 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Hirals BreezeP52100029974 | Pimpri Chinchawad (M Corp.) | 2021 | Certificate Signed | 31 Dec 2023 | 30 Dec 2024 | +12 months |
| 15 M StreetP52100030251 | Pimpri Chinchawad (M Corp.) | 2021 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Hirals Breeze (P52100029974).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology