Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vaishnave ClassicP52100019954Pimpri Chinchawad (M Corp.)2019Certificate Signed30 Jun 202330 Jun 2023On date
Harsh ApartmentP52100025753Pimpri Chinchawad (M Corp.)2020Certificate Signed30 Dec 202230 Dec 2022On date
Hirals BreezeP52100029974Pimpri Chinchawad (M Corp.)2021Certificate Signed31 Dec 202330 Dec 2024+12 months
15 M StreetP52100030251Pimpri Chinchawad (M Corp.)2021Certificate Signed31 Dec 202531 Dec 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vaishnave ClassicOn date
  • Harsh ApartmentOn date
  • Hirals Breeze+12 mo
  • 15 M StreetOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Hirals Breeze (P52100029974).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology