Malpani Properties

Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Green ParkP52100025390Fursungi2020Certificate Signed29 Aug 202429 Aug 2024On date
Green ParkP52100032284Fursungi2021Certificate Signed30 Jun 202530 Jun 2025On date
CelestiaP52100078194Fursungi2024Certificate Signed31 Dec 202830 Apr 2029+4 months
UnicusPM1260002500799Fursungi2025Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Green ParkOn date
  • Green ParkOn date
  • Celestia+4 mo
  • UnicusOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Celestia (P52100078194).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology