Malkhare Builders And Developers Pvt Ltd
Company or firm · 4 projects · 4 MahaRERA registrations · 1 reported completed
4Projects4 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| NakshtranganP51500031479 | Aurangabad (M Corp.) | 2021 | Certificate Signed | 31 Mar 2025 | 31 Mar 2025 | On date |
| VishwasP51500048551 | Aurangabad (M Corp.) | 2023 | Completed | 31 Mar 2027 | — | On date |
| Nakshtrangan AnuradhaP51500053699 | Aurangabad (M Corp.) | 2023 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Urban NestPR1040002601980 | Itkheda | 2026 | Not reported | 31 Dec 2032 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Nakshtrangan Anuradha (P51500053699).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology