Maitreya Developers

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+17 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Orange City Park IIP50500017849Yerkheda (Ct)2018Not reported1 Feb 20221 Feb 2023+12 months
Orange City Park IIIP50500023595Yerkheda (Ct)2019Not reported28 Nov 202326 Sep 2025+22 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Orange City Park II+12 mo
  • Orange City Park III+22 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 22 months, for Orange City Park III (P50500023595).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology