Maitreya Developers
Company or firm · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+17 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Orange City Park IIP50500017849 | Yerkheda (Ct) | 2018 | Not reported | 1 Feb 2022 | 1 Feb 2023 | +12 months |
| Orange City Park IIIP50500023595 | Yerkheda (Ct) | 2019 | Not reported | 28 Nov 2023 | 26 Sep 2025 | +22 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 22 months, for Orange City Park III (P50500023595).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology