Mahir Builders And Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mahir PlazaP52000010484Taloje Panchnad2017Certificate Signed31 Dec 201930 Mar 2021+15 months
Paramount HeightP52000010767Taloje Panchnad2017Certificate Signed30 Nov 202030 Nov 2020On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mahir Plaza+15 mo
  • Paramount HeightOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 15 months, for Mahir Plaza (P52000010484).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology