Maheshwar Enterprises

Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shivram AvenueP51600010957Nashik2017Not reported31 Dec 2020—On date
Shivganga HeightsP51600022074Nashik (M Corp.)2019Completed28 Aug 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shivram AvenueOn date
  • Shivganga HeightsOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology