Individual promoter · 8 projects · 8 MahaRERA registrations · 1 reported completed
8Projects8 RERA registrations
1Completedas reported on MahaRERA project pages
86%Kept RERA date6 of 7 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kamdhenu Prasad CHS Ltd.P51700008269 | Thane (M Corp.) | 2017 | Completed | 31 Jan 2018 | — | On date |
| Gautam Co-operative Housing SocietyP51700009938 | Thane (M Corp.) | 2017 | Certificate Signed | 31 Jul 2018 | 31 Jul 2018 | On date |
| Madhuban Co-operative Housing Society Ltd.P51700014337 | Thane (M Corp.) | 2017 | Certificate Signed | 30 Dec 2020 | 30 Jun 2022 | +18 months |
| Trushna Chs LtdP51700023568 | Thane (M Corp.) | 2019 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Mayur Chs LtdP51700024371 | Thane (M Corp.) | 2020 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Satyabhama CHS LTDP51700032055 | Thane (M Corp.) | 2021 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Thane Shivam Chs LtdP51700048226 | Thane (M Corp.) | 2022 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Jivan Shanti Chs LtdP51700054674 | Thane (M Corp.) | 2024 | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 6 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Madhuban Co-operative Housing Society Ltd. (P51700014337).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.