Maharashtra Housing Development Corporation Limited

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mhdc Jv Majrewadi Solapur Pmay ProjectP52600028338Solapur (M Corp.)2021Not reported22 May 2024—On date
Mhdcl Antrolikar Nagar Solapur Pmay ProjectP52600034859Solapur (M Corp.)2022Not reported30 Apr 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mhdc Jv Majrewadi Solapur Pmay ProjectOn date
  • Mhdcl Antrolikar Nagar Solapur Pmay ProjectOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology