Company or firm · 5 projects · 5 MahaRERA registrations · 1 reported completed

Also appears as MADHOOR BUILDWELL PRIVATE LIMITED · Madhoor Buildwell Pvt. Ltd.

5Projects5 RERA registrations
1Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Beverlly Hills Phase - IIIP51600000718Nashik (M Corp.)2017Completed30 Sep 2022—On date
Madhoors AnandamP51600001270Nashik (M Corp.)2017Not reported31 Mar 202431 Dec 2026+33 months
Madhoors Talekar ChamberP51600017279Nashik (M Corp.)2018Certificate Signed30 Jun 202131 Aug 2023+26 months
Shri Laxmi Narayan VillasP51600051490Dasak2023Certificate Signed31 Dec 202730 Apr 2028+4 months
Madhoor AurumP51900077613Ward Fnorth2024Not reported30 Jun 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Beverlly Hills Phase - IIIOn date
  • Madhoors Anandam+33 mo
  • Madhoors Talekar Chamber+26 mo
  • Shri Laxmi Narayan Villas+4 mo
  • Madhoor AurumOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 33 months, for Madhoors Anandam (P51600001270).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology