M & R Infra Pavers Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Radhika Vihar MadhubanP50500017657Waddhamna2018Not reported28 Aug 2023—On date
Radhika Vihar Krishna VatikaP50500032408Waddhamna2022Not reported31 Mar 2026—On date
Radhika Vihar - WaddhamanaPP1190002600382Waddhamna2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Radhika Vihar MadhubanOn date
  • Radhika Vihar Krishna VatikaOn date
  • Radhika Vihar - WaddhamanaOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology