M M Enterprises

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hayaat GreenP99000003365Vasaivirar City (M Corp)2017Not reported20 Mar 201820 Mar 2019+12 months
Hayaat GalaxyP99000003445Vasai Virar City (M Corp)2017Not reported31 Dec 201930 Dec 2021+24 months
Hayaat GardenP99000006530Vasaivirar City (M Corp)2017Not reported30 Mar 2018—On date
Hayaat Galaxy IIP99000030622Vasai Virar City (M Corp)2021Not reported30 Nov 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hayaat Green+12 mo
  • Hayaat Galaxy+24 mo
  • Hayaat GardenOn date
  • Hayaat Galaxy IIOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Hayaat Galaxy (P99000003445).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology