M M Enterprises
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Hayaat GreenP99000003365 | Vasaivirar City (M Corp) | 2017 | Not reported | 20 Mar 2018 | 20 Mar 2019 | +12 months |
| Hayaat GalaxyP99000003445 | Vasai Virar City (M Corp) | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Hayaat GardenP99000006530 | Vasaivirar City (M Corp) | 2017 | Not reported | 30 Mar 2018 | — | On date |
| Hayaat Galaxy IIP99000030622 | Vasai Virar City (M Corp) | 2021 | Not reported | 30 Nov 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Hayaat Galaxy (P99000003445).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology