M D Constructions
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sky View Ph 1P52100010942 | Pune (M Corp.) | 2017 | Not reported | 31 Dec 2017 | 31 Dec 2018 | +12 months |
| Nalanda Garden B WingP52100031155 | Baner | 2021 | Not reported | 30 Sep 2022 | 30 Sep 2023 | +12 months |
| Brahma Tower I A and B WingP52100050139 | Wakad | 2023 | Not reported | 31 Mar 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Sky View Ph 1 (P52100010942).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology