Lotus Logistics And Developers Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as Lotus Logistics And Developers Pvt Ltd

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+33 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Lotus Sky GardenP51800005655Borivali2017Not reported30 Jun 2027—On date
Lotus ResidencyP51800006322Mumbai2017Not reported30 Jun 202131 Dec 2024+42 months
Unity by LotusP51800006403Andheri2017Not reported30 Sep 202030 Jun 2023+33 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Lotus Sky GardenOn date
  • Lotus Residency+42 mo
  • Unity by Lotus+33 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Lotus Residency (P51800006322).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology