Lnk Projects Through Proprietor Mr Narayan Baburao Khasnis

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
The Back Water Residency phase I - D BuildingP52100019828Khanapur2019Certificate Signed27 Dec 201927 Mar 2021+15 months
The Back Water Residency Phase II - B BuildingP52100031341Khanapur2021Certificate Signed27 Dec 202527 Dec 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • The Back Water Residency phase I - D Building+15 mo
  • The Back Water Residency Phase II - B BuildingOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 15 months, for The Back Water Residency phase I - D Building (P52100019828).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology