Lnk Projects Through Proprietor Mr Narayan Baburao Khasnis
Individual promoter · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| The Back Water Residency phase I - D BuildingP52100019828 | Khanapur | 2019 | Certificate Signed | 27 Dec 2019 | 27 Mar 2021 | +15 months |
| The Back Water Residency Phase II - B BuildingP52100031341 | Khanapur | 2021 | Certificate Signed | 27 Dec 2025 | 27 Dec 2025 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 15 months, for The Back Water Residency phase I - D Building (P52100019828).
Regulatory cases across projects
- DeregisteredDeregistered: The Back Water Residency Phase II - B Building · The Back Water Residency Phase II - B Building · P52100031341
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology