Lifespace Realty

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Victoria House Phase IP51700008522Ambarnath (R)2017Not reported30 Jun 201831 Jan 2019+7 months
Villas Delphin Phase II - Type IP51700019289Ambarnath2019Not reported30 Dec 2022—On date
Villas Delphin Phase I - Type IIP51700019353Ambarnath (R)2019Not reported30 Mar 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Victoria House Phase I+7 mo
  • Villas Delphin Phase II - Type IOn date
  • Villas Delphin Phase I - Type IIOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 7 months, for Victoria House Phase I (P51700008522).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology