Lifecraft Realty

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
The 4th AxisP52100049095Pimpri Chinchawad (M Corp.)2023Certificate Signed1 Dec 20261 Apr 2027+4 months
The 4th AxisP52100056110Pimpri Chinchawad (M Corp.)2024Certificate Signed25 Dec 202725 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • The 4th Axis+4 mo
  • The 4th Axis+4 mo

Track record notes

  • Longest extension on record: 4 months, for The 4th Axis (P52100049095).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology