Leela Associates

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vasant LeelaP52000050609Khopoli2023Certificate Signed31 Mar 202731 Mar 2027On date
GardeniaPM1270002502153Khopoli2026Certificate Signed30 Sep 203030 Jan 2031+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vasant LeelaOn date
  • Gardenia+4 mo

Track record notes

  • Longest extension on record: 4 months, for Gardenia (PM1270002502153).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology