Laxmikantan R Venkatraman

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Eden GardenP52000015065Poyanje2018Certificate Signed31 Dec 201930 Dec 2021+24 months
Eden Garden Phase -IIP52000028297Poyanje2021Certificate Signed30 Mar 202230 Mar 2022On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Eden Garden+24 mo
  • Eden Garden Phase -IIOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Eden Garden (P52000015065).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology