Skip to content

Laxmi Developments

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Laxmi Emerald C WingP52100033122Lohgaon2022Certificate Signed31 Dec 202631 Dec 2026On date
Laxmi Emerald D WingP52100076689Lohgaon2024Certificate Signed31 Dec 202731 Dec 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Laxmi Emerald C WingOn date
  • Laxmi Emerald D WingOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology