Laxmi Builders
Company or firm · 5 projects · 5 MahaRERA registrations
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%5 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vakratund ResidencyP51600024284 | Nashik | 2020 | Not reported | 9 Jan 2023 | — | On date |
| Ekadanta PrideP51600026874 | Nashik (M Corp.) | 2020 | Not reported | 30 Apr 2024 | — | On date |
| Mangalmurti ResidencyP51600030199 | Nashik (M Corp.) | 2021 | Not reported | 31 Jul 2023 | — | On date |
| Parvati AnnexP51600030650 | Nashik (M Corp.) | 2021 | Not reported | 30 Apr 2024 | — | On date |
| Lambodar AnnexP51600032830 | Nashik (M Corp.) | 2022 | Not reported | 31 Dec 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- DeregisteredDeregistered: Lambodar Annex · Lambodar Annex · P51600032830
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology