Lashkaria Housing & Infrastructure Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Lashkaria AnuragP51800008422Andheri2017Not reported1 Aug 2019—On date
Lashkaria EmpressP51800010789Andheri2017Not reported30 Jun 201911 May 2023+47 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Lashkaria AnuragOn date
  • Lashkaria Empress+47 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 47 months, for Lashkaria Empress (P51800010789).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology