Lashkaria Housing & Infrastructure Private Limited
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Lashkaria AnuragP51800008422 | Andheri | 2017 | Certificate Signed | 1 Aug 2019 | 1 Aug 2019 | On date |
| Lashkaria EmpressP51800010789 | Andheri | 2017 | Certificate Signed | 30 Jun 2019 | 11 May 2023 | +47 months |
| Lashkaria PearlP51800023377 | Andheri | 2019 | Certificate Signed | 1 Nov 2026 | 1 Mar 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 47 months, for Lashkaria Empress (P51800010789).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology