Lashkaria Housing & Infrastructure Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Lashkaria AnuragP51800008422Andheri2017Certificate Signed1 Aug 20191 Aug 2019On date
Lashkaria EmpressP51800010789Andheri2017Certificate Signed30 Jun 201911 May 2023+47 months
Lashkaria PearlP51800023377Andheri2019Certificate Signed1 Nov 20261 Mar 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Lashkaria AnuragOn date
  • Lashkaria Empress+47 mo
  • Lashkaria Pearl+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 47 months, for Lashkaria Empress (P51800010789).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology