Landscape Reality

Company or firm · 1 project · 3 MahaRERA registrations

1Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AnantsrishtiP52100006401Jambhul2017Certificate Signed31 Mar 201930 Sep 2020+18 months
AnantsrishtiP52100015964Jambhul2018Certificate Signed30 Mar 202130 Mar 2021On date
AnantsrishtiP52100015968Jambhul2018Certificate Signed30 Jun 202230 Jun 2022On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anantsrishti+18 mo
  • AnantsrishtiOn date
  • AnantsrishtiOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Anantsrishti (P52100006401).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology