Lagoo Apte
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| GopalkrupaP52100003479 | Karve Nagar | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| VasudevsmrutiP52100014160 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| ShreeniwasP52100014480 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | On date |
| MauliP52100016610 | Pune (M Corp.) | 2018 | Certificate Signed | 31 Jul 2022 | 31 Jul 2022 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
