Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
ShreeyashP52100080803Erandwane South2025Certificate Signed30 Jan 202930 Jan 2029On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • ShreeyashOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.