Lachhman Vasdev Bathija
Individual promoter · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Siddhivinayak TwinsP52000003619 | Kalamboli | 2017 | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Siddhivinayak HeightsP52000006905 | Kalamboli | 2017 | Certificate Signed | 31 Jul 2018 | 31 Jul 2018 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Mr. Lachhman Vasdev Bathija (Suo Motu Case No. 55 of 2020) dated 10th February 2020 · Siddhivinayak Twins · P52000003619 · 11 Feb 2020
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology