Skip to content

L&T Seawoods Limited

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
L And T Seawoods Residences Phase IP51700020275Thane2019Certificate Signed30 Dec 202430 Dec 2024On date
L And T Seawoods Residences - North TowersP51700026653Navi Mumbai (M Corp.)2020Certificate Signed30 Dec 202430 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • L And T Seawoods Residences Phase IOn date
  • L And T Seawoods Residences - North TowersOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology