L. K. Realtors

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Bhagyashree BuildingP51700026950Thane (M Corp.)2020Not reported1 Aug 202231 Jul 2023+11 months
Diwa Swapna Co. Op. Housing SocietyP51700050021Thane (M Corp.)2023Not reported31 Jul 2025—On date
Pranjali Co-Operative Housing Society LimitedPR1330002502772Thane (M Corp.)2026Not reported31 Mar 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Bhagyashree Building+11 mo
  • Diwa Swapna Co. Op. Housing SocietyOn date
  • Pranjali Co-Operative Housing Society LimitedOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 11 months, for Bhagyashree Building (P51700026950).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology