Kumar Builders
Company or firm · 4 projects · 7 MahaRERA registrations
Projects47 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date57%4 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| KUL Utsav Phase I -Building GP52100003489 | Kondhwa Bk | 2017 | Not reported | 15 May 2019 | 30 Jun 2023 | +49 months |
| Kul UtsavP52100007155 | Kondhwa Bk | 2017 | Not reported | 26 Oct 2020 | — | On date |
| Kul UtsavP52100007157 | Kondhwa Bk | 2017 | Not reported | 15 May 2019 | 14 Nov 2020 | +18 months |
| Kul UtsavP52100007160 | Kondhwa Bk | 2017 | Not reported | 15 May 2019 | 30 Oct 2020 | +17 months |
| Windsor ParkP52700007156 | Bhose | 2017 | Not reported | 30 Dec 2023 | — | On date |
| KUL CoutureP51900009276 | Mumbai City | 2017 | Not reported | 30 Dec 2024 | — | On date |
| Kul UtsavP52100009849 | Kondhwa Bk | 2017 | Not reported | 23 Dec 2019 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 49 months, for KUL Utsav Phase I -Building G (P52100003489).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology