Kumar Builders

Company or firm · 4 projects · 7 MahaRERA registrations

Projects47 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date57%4 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
KUL Utsav Phase I -Building GP52100003489Kondhwa Bk2017Not reported15 May 201930 Jun 2023+49 months
Kul UtsavP52100007155Kondhwa Bk2017Not reported26 Oct 2020—On date
Kul UtsavP52100007157Kondhwa Bk2017Not reported15 May 201914 Nov 2020+18 months
Kul UtsavP52100007160Kondhwa Bk2017Not reported15 May 201930 Oct 2020+17 months
Windsor ParkP52700007156Bhose2017Not reported30 Dec 2023—On date
KUL CoutureP51900009276Mumbai City2017Not reported30 Dec 2024—On date
Kul UtsavP52100009849Kondhwa Bk2017Not reported23 Dec 2019—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • KUL Utsav Phase I -Building G+49 mo
  • Kul UtsavOn date
  • Kul Utsav+18 mo
  • Kul Utsav+17 mo
  • Windsor ParkOn date
  • KUL CoutureOn date
  • Kul UtsavOn date

Track record notes

  • 4 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 49 months, for KUL Utsav Phase I -Building G (P52100003489).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology