Kumar Builders Consortium

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shantiniketan Phase II A3P52100005467Pashan2017Certificate Signed9 Mar 20199 Mar 2020+12 months
Shantiniketan Phase II A4P52100006736Pashan2017Certificate Signed9 Mar 20199 Mar 2020+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shantiniketan Phase II A3+12 mo
  • Shantiniketan Phase II A4+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Shantiniketan Phase II A3 (P52100005467).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology