Kulshree Builders
Company or firm · 1 project · 2 MahaRERA registrations
1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+31 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Deshpande GardenP52100013986 | Wadgaon Bk | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Deshpande GardenP52100014001 | Wadgaon Bk | 2017 | Certificate Signed | 30 Dec 2022 | 28 Feb 2028 | +62 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 62 months, for Deshpande Garden (P52100014001).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology