Kukreja Construction Co

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
GeetanjaliP51800000280Kurla2017Not reported31 Dec 2017—On date
Chembur Heights IIP51800001916Kurla2017Not reported30 Jun 201929 Dec 2021+30 months
Hari Kunj IIIP51800007495Kurla2017Not reported30 Sep 2020—On date
Sai Ashish IIP51800009725Kurla2017Not reported31 Dec 2017—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • GeetanjaliOn date
  • Chembur Heights II+30 mo
  • Hari Kunj IIIOn date
  • Sai Ashish IIOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Chembur Heights II (P51800001916).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology