Kukreja Construction Co
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| GeetanjaliP51800000280 | Kurla | 2017 | Not reported | 31 Dec 2017 | — | On date |
| Chembur Heights IIP51800001916 | Kurla | 2017 | Not reported | 30 Jun 2019 | 29 Dec 2021 | +30 months |
| Hari Kunj IIIP51800007495 | Kurla | 2017 | Not reported | 30 Sep 2020 | — | On date |
| Sai Ashish IIP51800009725 | Kurla | 2017 | Not reported | 31 Dec 2017 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 30 months, for Chembur Heights II (P51800001916).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology