Kripa Oneness Private Limited
Company or firm · 5 projects · 5 MahaRERA registrations
Also appears as Kripa Oneness Pvt. Ltd.
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kripa AllureP51800018912 | Andheri | 2018 | Certificate Signed | 30 May 2022 | 30 May 2022 | On date |
| Kripa VueP51800034034 | Andheri | 2022 | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Kripa AquaPR1180002502548 | Bandra | 2026 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Kripa OasisPM1180002502588 | Bandra | 2026 | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 months |
| Kripa JewelPR1180002601267 | Bandra | 2026 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Kripa Aqua (PR1180002502548).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology