Kosmos Developer

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 3 past their proposed date, not extended
Median delay+33 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vinayak TowerP51800009164Borivali2017Not reported31 Dec 201930 Jun 2023+42 months
Shreeyog ChslP51800009351Borivali2017Not reported31 Dec 201930 Jun 2023+42 months
NandanvanP51800012073Borivali2017Not reported30 Jun 202130 Jun 2023+24 months
Express Tower CHSP51800051077Borivali2023Not reported16 Feb 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vinayak Tower+42 mo
  • Shreeyog Chsl+42 mo
  • Nandanvan+24 mo
  • Express Tower CHSOn date

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Vinayak Tower (P51800009164).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology