Konark Associates
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Blue BreezeP52100006216 | Thergaon | 2017 | Not reported | 31 Dec 2018 | 30 Dec 2020 | +24 months |
| Yashoda AanganP52100006664 | Thergaon | 2017 | Not reported | 31 Dec 2019 | 30 Jun 2023 | +42 months |
| Grand CasaP52100009837 | Thergaon | 2017 | Not reported | 30 Apr 2021 | 30 Oct 2022 | +18 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 42 months, for Yashoda Aangan (P52100006664).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology