Konark Associates

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Blue BreezeP52100006216Thergaon2017Not reported31 Dec 201830 Dec 2020+24 months
Yashoda AanganP52100006664Thergaon2017Not reported31 Dec 201930 Jun 2023+42 months
Grand CasaP52100009837Thergaon2017Not reported30 Apr 202130 Oct 2022+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Blue Breeze+24 mo
  • Yashoda Aangan+42 mo
  • Grand Casa+18 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Yashoda Aangan (P52100006664).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology