Kishor Shankar Garve
Company or firm · 3 projects · 5 MahaRERA registrations
3Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Eastern River Residency Wing FP52100026039 | Pimpale Gurav | 2020 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Eastern River ResidencyP52100033276 | Pimpale Gurav | 2022 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Eastern River ResidencyP52100049815 | Pimpale Gurav | 2023 | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
| Eastern River Residency MHADA BuildingsP52100053566 | Pimpale Gurav | 2023 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Eastern River ResidencyP52100078700 | Pimpale Gurav | 2025 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Eastern River Residency (P52100033276).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology