Kirik Enterprises

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kirik Oriole Phase 1aP52100015859Wakad2018Certificate Signed30 Sep 202030 Mar 2022+18 months
Kirik Oriole Phase 1bP52100017872Wakad2018Certificate Signed30 Mar 202230 Mar 2022On date
Varun Enclave CHSP52100049179Pune (M Corp.)2023Certificate Signed31 Dec 202531 Dec 2025On date
Ambarish Apartment CondominiumP52100079622Pune (M Corp.)2025Certificate Signed28 Feb 202828 Jun 2028+4 months
Radhakrishna ApartmentsPR1260002600025Pune (M Corp.)2026Certificate Signed31 Mar 202831 Jul 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kirik Oriole Phase 1a+18 mo
  • Kirik Oriole Phase 1bOn date
  • Varun Enclave CHSOn date
  • Ambarish Apartment Condominium+4 mo
  • Radhakrishna Apartments+4 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Kirik Oriole Phase 1a (P52100015859).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology