Kiran Enterprises

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
New NanddhamP99000004153Vasaivirar City (M Corp)2017Certificate Signed30 Jun 202231 Mar 2023+9 months
Shri SaikripaP99000049609Sopara2023Certificate Signed31 Dec 202730 Apr 2028+4 months
Shri GaneshkripaP99000053717Sopara2023Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • New Nanddham+9 mo
  • Shri Saikripa+4 mo
  • Shri GaneshkripaOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 9 months, for New Nanddham (P99000004153).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology