Khushi Prime Estate Private Limited
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Khushi VistaraP53100056175 | Sangli Miraj Kupwad (M Corp.) | 2024 | Certificate Signed | 25 Jan 2027 | 25 May 2027 | +4 months |
| Khushi OneP53100081062 | Sangli Miraj Kupwad (M Corp.) | 2025 | Certificate Signed | 25 Sep 2028 | 25 Jan 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Khushi Vistara (P53100056175).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology