Keytech
Company or firm · 5 projects · 5 MahaRERA registrations
Also appears as M/S Keytech
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ashok Smruti DefgP51700000864 | Thane (M Corp.) | 2017 | Not reported | 31 Dec 2019 | — | On date |
| Key Tech ParkP51800000849 | Andheri | 2017 | Not reported | 30 Dec 2026 | — | On date |
| Jiten ChsP51800032184 | Andheri | 2021 | Not reported | 31 Dec 2024 | 31 Mar 2026 | +15 months |
| Vishakha Heights And Vishakha RegencyP51800046013 | Kurla | 2022 | Not reported | 30 Jun 2026 | — | On date |
| Om MayureshP51800052639 | Mulund | 2023 | Not reported | 31 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 15 months, for Jiten Chs (P51800032184).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology