Kedar Infra

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kedar Infra HousingP53000021963Kolhapur (M Corp.)2019Not reported30 Dec 2022—On date
Kedar ParkP53000034249Kolhapur (M Corp.)2022Not reported31 Dec 202431 Dec 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kedar Infra HousingOn date
  • Kedar Park+12 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Kedar Park (P53000034249).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology