Kcd And Synergy Ventures

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Palkhi AuraP51800009045Borivali2017Not reported31 Dec 201930 Dec 2021+24 months
Palkhi Aura - Part 18th To 22nd FloorP51800023699Borivali2020Not reported30 Dec 2022—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Palkhi Aura+24 mo
  • Palkhi Aura - Part 18th To 22nd FloorOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Palkhi Aura (P51800009045).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology