Kayum Ali Parkar
Individual promoter · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| West WindP52800005455 | Dapoli | 2017 | Certificate Signed | 1 Dec 2019 | 1 Dec 2019 | On date |
| Fatima ResidencyP52800023645 | Mauje Dapoli | 2019 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Hadi CornerP52800026506 | Dapoli Camp | 2020 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Abdul Gafoor ResidencyP52800045445 | Mauje Dapoli | 2022 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- Quarterly progress report not filedQuarterly progress report not filed: ABDUL GAFOOR RESIDENCY · Abdul Gafoor Residency · P52800045445
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology