Skip to content

Kashish Park Realtors

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kashish ParkP51700001799Thane (M Corp.)2017Certificate Signed30 Dec 202230 Dec 2022On date
Kashish ParkP51700028738Thane (M Corp.)2021Certificate Signed30 Jun 203030 Oct 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kashish ParkOn date
  • Kashish Park+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Kashish Park (P51700028738).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology