Kasa Builders & Contractor

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kasa VillageP52700016999Karanje Tarf Satara (Ct)2018Not reported30 Oct 202325 Oct 2024+12 months
Kasa RioP52100034199Baramati Rural2022Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kasa Village+12 mo
  • Kasa RioOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Kasa Village (P52700016999).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology