Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
SapphirePC1190002501236Nagpur (M Corp.)2025Certificate Signed31 Dec 202830 Apr 2029+4 months
SwastikPR1190002602147Nagpur (M Corp.)2026Certificate Signed31 Mar 203031 Mar 2030On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sapphire+4 mo
  • SwastikOn date

Track record notes

  • Longest extension on record: 4 months, for Sapphire (PC1190002501236).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.