Kamla Homes & Infrastructure
Company or firm · 2 projects · 2 MahaRERA registrations
Also appears as M/S. Kamla Homes & Infrastructure
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kamla Jainson Phase 1 Part Podium from 2nd to 4th floor and 5th to 25th habitable floorsP51800014629 | Borivali | 2017 | Certificate Signed | 30 Dec 2022 | 30 Dec 2023 | +12 months |
| Kamla Jainson Wing CP51800052711 | Malad | 2023 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Kamla Jainson Phase 1 Part Podium from 2nd to 4th floor and 5th to 25th habitable floors (P51800014629).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology