Kalyan Development Corporation

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+9 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mangeshi Dazzle - IIIP51700005137Kalyandombivali (M Corp.)2017Not reported31 Mar 201930 Sep 2020+18 months
Mangeshi Dazzle IIP51700024511Kalyandombivali (M Corp.)2020Not reported30 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mangeshi Dazzle - III+18 mo
  • Mangeshi Dazzle IIOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Mangeshi Dazzle - III (P51700005137).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology