Kalpataru Properties Limited
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kalpataru AzuroP51900045295 | Malabar Hill | 2022 | Not reported | 31 Dec 2027 | — | On date |
| Kalpataru One - Wing AP51900055246 | Mumbai City | 2024 | Certificate Signed | 31 Mar 2032 | 31 Jul 2032 | +4 months |
| Kalpataru One - Wing BP51900079410 | Ward Gsouth | 2025 | Not reported | 31 Mar 2032 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Kalpataru One - Wing A (P51900055246).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology