Kalpataru Properties Limited

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kalpataru AzuroP51900045295Malabar Hill2022Not reported31 Dec 2027—On date
Kalpataru One - Wing AP51900055246Mumbai City2024Certificate Signed31 Mar 203231 Jul 2032+4 months
Kalpataru One - Wing BP51900079410Ward Gsouth2025Not reported31 Mar 2032—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kalpataru AzuroOn date
  • Kalpataru One - Wing A+4 mo
  • Kalpataru One - Wing BOn date

Track record notes

  • Longest extension on record: 4 months, for Kalpataru One - Wing A (P51900055246).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology