Kalpana StructCon Infra Llp

Company or firm · 1 project · 1 MahaRERA registration

Also appears as KALPANA STRUCT-CON INFRA LLP

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+27 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
NestorP52000014902Bokadvira2018Certificate Signed30 Dec 202229 Mar 2025+27 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nestor+27 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 27 months, for Nestor (P52000014902).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology